|
| |
|
Year 4 - March
2003 - COMPLETION |
| March 8, 2003, 4:00 pm: Three deck
pieces have been added this week and as the pieces are welded together,
they no longer have the curved appearance as before. The tricky move
involving the Vallejo deck is almost complete and you can see from the
center photo that it is almost in place. The photo on the right
shows how the crane has dropped the strand jacks to the barge
below. The tug will now shuttle them over to Mare Island for
cleaning before they are used to hoist the next piece. Deck lifts
seem to be almost routine now.
Click on the photos to enlarge them. |
|
From the Maritime Academy you can see
the last Vallejo deck piece almost in place. It was another great day
for bridge viewing and people are still coming from all over the Bay
Area to watch the construction progress. |

|

|
| April 2, 2003, 4:57
pm: Three more decks are waiting to be raised on
the Crockett side. The last three had to be slid into place through the
tower legs. Next they will be lifted into place using strand jacks. In
the picture on the right you can see one deck piece inside the tower
legs and the others below it. These were the last deck pieces from
Japan. |
| May 9, 2003, 3:53: These
pictures below are a series of shots of an I-beam being raised. Alot of
work is being done on the bridge approach to get it connected to the
bridge deck. |
|
|
|

|
Can you find the worker? If you click
in the picture to the left, you can find an iron worker working on the
connector ramp waiting to receive the I-Beam from the crane. He is
working right over the anchorage. |
|

|

|

|
| All the pieces of the bridge
deck are now attached to suspender cables. The last pieces on the
Crockett side still need a little tweaking to get them into place.
That's why you still see the strand jacks there. The bridge deck
has a curve to it which is normal. It is higher than we expected
and is slightly higher than the decks of the other bridges. You
can see people working on the deck as you drive by. Now workers
are performing the task of wrapping the main cable. First they put
a protective coating on the cable bundles and then they wrap it with a
thinner wire. They started this in the middle and working back toward
the two towers. Follow this link to ironworker Dick McCabe, Jr.'s sight
to see some great up-close and personal photos from someone who is
actually doing this work. http://www.ironmc.com/main.htm |
| What's next? After
some design changes, the rails are beginning to be manufactured and they
will be installed. The deck pieces are being welded together and
the bridge deck is being prepared for a special asphalt coating.
The bridge cables will be painted red and the railings will be
green. These colors were chosen by a citizen's advisory committee
in Crockett after they saw a series of drawings in various colors. |
|
DECK
TOUR--June 2, 2003 |
|

|
Not so long ago, on a beautiful spring day,
we attended the groundbreaking ceremony for the new bridge. Today, we
were invited to actually walk on the deck--what a tremendous feeling we
had! We walked onto the deck from the Vallejo side. Again,
it was another beautiful spring day. On this tour we took along a Hogan
High School film crew. They filmed us on tour and later produced a
short piece for the school's "Morning Show." In this picture
you can see one of the workers on a bike. Since their work takes
them back and forth across the span, the workers have bicycles so they
don't have to walk so far. |
| Before we began our tour, Bart
gave us a little update about the progress of the bridge. Since
the deck is now all raised into place, ironworkers are busy welding each
piece together. The deck surface itself is being cleaned up and
prepared for the layer of asphalt which will be the road surface.
Permanent electrical wiring is being installed on the deck for lighting
and other power needs. Inside the towers, stairs are being
installed for maintenance crews. The main cables are being cleaned
and prepped for painting. The next main construction project will be the
final connection of the bridge deck with the Crockett interchange. There
are two expansion joints at both ends of the bridge that will be
completed as well. Finally, the guardrails are being manufactured
and painted and will soon be arriving for installation.
The following are pictures taken from
our tour. Click on them to see them bigger. |
|

|

|

|
| Before we went onto the deck, we went under
it to see how the deck pieces have been welded together. |
Under the bridge you can see that there is
still work to be done. A concrete bumper has been constructed to
protect the tower from a collision with a ship. |
We also got a good look at the main cables
as they are splayed before entering the anchorage. Last time we
were here, there were only a few cables. |
|

|

|

|
| This is what the welded sections look like
from the top. |
We took a look at one of the two expansion
joints. Unlike other bridges that have spaces between each deck
piece, the new bridge has only two high-tech expansion joints. |
Bart showed us part of the mechanism of the
expansion joint under the bridge deck. |
|

|

|

|
| We were surprised to see that
the cables are attached to the bridge deck with what looked like simple
nuts, bolts and cotter pins we've seen before but MUCH BIGGER! |
The deck still has a curved appearance and
when you are walking on it, it looks like an uphill trek to the center.. |
|

|

|

|
| Let's hope that they raise the speed limit
on the bridge, or else the CHP will be very busy writing tickets for
speeders! |
Graffiti on the bridge already? No! These
are marks made by the Japanese ironworkers who constructed the deck
sections in Japan. Notice that they have been doused with good old
American coffee by our ironworkers! |
Filming us, filming them? Caltrans is
documenting the building of the bridge and all the people involved in
its construction--including us! |
|

|

|

|
| We posed with Bart, our tour guide.
Notice the cool shades we had to wear to protect us from the glare on
the deck. Safety first! We had to be always aware of what was
around us, above us, and at our feet. |
Once we were on the deck, we just enjoyed
looking at the new views we had of our North Bay region. As
pedestrians, everyone walking across the bridge will be able to enjoy
this view. |
Besides car and foot traffic, the new
bridge will continue to allow ships like this to pass under it on their
way to inland ports at Benicia, Martinez, Sacramento, and Stockton. Oil,
automobiles and other goods enter the San Francisco Bay and travel
through the Carquinez Straits. |
|
Painting
the Cables, July 3, 2003 |
| It's hard to tell from these shots but the
farthest main cable has already been painted from the south tower to
about the center of the bridge. Some of the suspender cables have
been painted too. Some people say the color is like the Golden Gate
Bridge, but actually it is darker--a richer reddish orange. |
| We are all excited about the prospect of
the bridge opening in late October, early November. We've been
appearing at local elementary schools, teaching and sharing what we know
about suspension bridges and how they are built. Students are now
looking forward to the grand opening with fireworks and other
activities. We all want to ride our bicycles across the new deck too! |
|